Work continues on Phase 1 of Beach Houses with the structures of units 4122/23 and 4132/33 now complete!
Work is continuing on the progression of the structures of units 4124/25 and 4130/31 while tiling in units 4134/35 and 4138/39 will begin this month, along with the installation of windows and doors.
The top of the box drain adjacent to unit 4128/29 has been cast, which will now allow the team to progress with the substructure of this unit. External works on the road and retaining wall of the Second Row are also continuing.